Thursday, June 4, 2009

Thursday 20090604

Not much going on today except the engineers finally were able to devise a solution to a deck framing problem that was created when the framing crew had to redo the deck girder connections to the pilings. The four knee braces and a haunch were the solution. Hopefully this will pass the framing inspection tomorrow and we can get on with the insulation. We selected Sellers Tile to set the tile in the baths and back entry/pantry. All other floors will be oak sanded and finished with Waterlox by Newsome Hardwood Floors.

No comments: