Finally, the floor framing inspection has been completed and passed! After lunch today, the framing crew came back to straightened the deck rails and start wrapping the front porch columns. They also finished fabricating and installing most of the piling caps for the deck railing. They will complete the railing once they remove the scaffolding and complete the column wrapping. Because the HVAC mechanical rough-in had not been inspected, the final framing inspection could not be completed today. The mechanical is scheduled for Monday and the final framing for Tuesday. That should mean that the insulation can be installed starting Wednesday.