Wednesday, September 23, 2009

Wednesday 20090923

Yesterday was a rain-out, but today lots was accomplished. Also, some things were done Monday that we could not take photos of until today.
  • Mirrors, towel bars, and shelves up in baths
  • Final electrical, plumbing, and mechanical inspections passed
  • Shoe molding being installed
  • Second coat of Waterlox(R) on floors
  • Final wall and trim paint in-progress
  • Parking area back steps completed
  • Interior door hardware installed
  • Bifold doors for laundry area installed