Tuesday, September 15, 2009

Tuesday 20090915

Not a real good day; mainly because the hardwood floor finishing crew never showed up. Gas Tech will have the underground LP tank delivered Friday. Gardner Welty Concrete marked the driveway and will form it on Thursday and pour either Thursday or Friday. We are meeting Floral Landscaping tomorrow at 10:00 to get another quote. The GC feels certain we can get a C.O. next week sometime. If so, we will be moving between September 25 and October 1. Progress Energy's cable contractor showed up today to measure for the power service, which should go in Thursday or Friday.