Thursday, July 2, 2009

Thursday 20090702

We met with the construction superintendent and the contractor at 7:30 this morning and went over where to place blocking for towel bars, handicap bars, and curtain rod holders. We also discussed the trim and AV cabinetry over the fireplace. The insulation inspector came around 9:00 and everything was OK except that they need to spray the foam in the attic with a fire resistant sealer. He gave us the go-ahead for the sheetrock and they will be here Tuesday to start that. The AV installer will be here at noon on Monday to install cable, phone and data lines. Here are some photos of a small portion of the blocking.


Wally cuts some studs for the AV cabinetry.

Mike does most of the cutting for all of the crew.

Dixie jealously guards Mike.