Thursday 20090430

Repair/adjustment of the fascia and trim has begun, but so far there does not seem to be much improvement other than getting rid of the notched intersection at the apex. Only about 2 sq ft of shake panels left to install on the west main gable.


Lap boards and trim on the rear downstairs are complete.

When the door flashing comes in, the doors can be re-installed and the last of the trim over the door and windows on the east wall can be installed, completing the downstairs on that side.

At last, the slab inspection is complete and it will be poured tomorrow.

Hannah and Emma placed some "archives" in the northeast corner of the slab.

Front wall downstairs is also waiting on door flanges.

We're on a roll! We hate to see the weekend come to slow the crew down.