Tuesday, March 31, 2009

Construction Day 047

Tuesday, March 31 resulted in much progress in flashing installation as well as some addtional plumbing.









Monday, March 30, 2009

Construction Day 046

A good bit more trim work today and the plumber put in a lot of the hot and cold water lines.





Friday, March 27, 2009

Construction Day 045

Some new exterior trim work was done today in spite of the weather. Duct tape has been put on all the exterior door thresholds to protect them during construction. More HVAC ducting went in to day as well.




Thursday, March 26, 2009

Construction Day 044

Another rainy day, but some more work outside, second air handler set, and the fireplace vent was installed.





Wednesday, March 25, 2009

Construction Day 043

Trim is looking real good!




One of the air handlers was set today.

Tuesday, March 24, 2009

Construction Day 042

Lots of new fascia, soffit panels, and trim boards.

More shingles installed.

Front porch flooring completed.

Cabinet outlines on kitchen subfloor...

... and master bath.




Monday, March 23, 2009

Construction Day 041

HVAC started today!


Roofing continued.

Soffit and facia started today.

Saturday, March 21, 2009

Construction Day 040

Actually got some of the shingles installed today.
Nate got the back steps installed down to the landing and turn toward the parking area.
Still can't get over the awesome view from the master bedroom.

Friday, March 20, 2009

Construction Day 039

Well, they put the shingles on the roof today; LITERALLY, they carried the bundles up to the roof and strategically placed them for installation! Lots of new flashing, 2x12 bands, and front porch decking to show for today as well.

Framing was begun on some steps from the parking area up to the back deck.


The fireplace was installed today.
Unfortunately, the last three doors are still not hung.

Thursday, March 19, 2009

Construction Day 038

All the windows are in, only three more doors to go, most of the roof overhangs have been boxed, the 2x12 bands are in place, shingles may go on tomorrow.



Wednesday, March 18, 2009

Construction Day 037

More zip system taping, return boxing, and window installation today.


Only one window and three exterior doors to install until it is dried-in.

Plumbing rough-in began today.