Well, still no CO. However, the landscaping is done except for a few rolls of sod. It is so disappointing not to be able to move in yet.
Wednesday, September 30, 2009
Tuesday, September 29, 2009
Tuesday 20090929
Still waiting on the CO; some controversy over the 2009 vs 2007 code in regard to the Zip system roof and spray-in foam insulation. Rough clean-up was begun yesterday and finished today. The painters finished interior touch-ups yesterday and the interior trim carpenter removed the flexible shoe molding around the 1st stair step riser. Today, Progress Energy put-in the meter, the last coat of floor finish was applied, and the landscaper continued the work they began yesterday.
Saturday, September 26, 2009
Friday, September 25, 2009
Thursday 20090924
No highly visible accomplishments today.
- More final painting
- All final inspections except whole house passed
Wednesday, September 23, 2009
Wednesday 20090923
Yesterday was a rain-out, but today lots was accomplished. Also, some things were done Monday that we could not take photos of until today.
- Mirrors, towel bars, and shelves up in baths
- Final electrical, plumbing, and mechanical inspections passed
- Shoe molding being installed
- Second coat of Waterlox(R) on floors
- Final wall and trim paint in-progress
- Parking area back steps completed
- Interior door hardware installed
- Bifold doors for laundry area installed
Monday, September 21, 2009
Monday 20090921
Busy, busy day.
- driveway poured
- interior door hardware, mirrors, towel bars, shelves installed
- gas piping to water heater and gas logs completed
- excavation for gas tank started
- plumbing final inspection passed
- minor discrepancies on electrical and mechanical finals
- second coat of finish applied to floors
Saturday, September 19, 2009
Thursday, September 17, 2009
Thursday 20090917
- Gardner Welty started grading and driveway form
- Newsome's Hardwood Floors continued sanding
- Progress energy installed line from power pole to service box
- Trenching uncovered the location of irrigation pipes
- Rennai tankless water heater installed except for gas connection