Monday, August 31, 2009

Monday 20090831

Not bad for a rainy day:
  • One of the HVAC outside units was installed along with several vents
  • The cooktop hood was installed
  • Barbara and I put the pantry tub sink together (Sunday afternoon)
  • All the registers and return vent grills were installed
  • Both thermostats were installed
  • The painters filled most of the finishing nail holes in the interior trim





Thursday, August 27, 2009

Thursday 20090827

Interior trim is done for now:
  • Front door from old house is now the pantry door
  • Stairs and rails are in
  • All chair rails are in
  • The equipment boxes are installed on either side of the fireplace









Wednesday, August 26, 2009

Wednesday 20090826

Leaving for Morehead City in a few minutes for the Coastal Resources Commission meeting so I went by the house a little early. We are getting real close now.
  • Last gable bracket is up
  • Mirrors in bath #2 are up
  • Chair rail in dining room and vestibule is up
  • Crown molding around top of appliance cabinets is up
  • All the wainscoting in bath #3 is up









Tuesday, August 25, 2009

Tuesday 20090825

Pretty good work done today.
  • upstairs stairwell hand rail completed
  • TV "box" set
  • Linen closet "box" set
  • Newel at bottom of steps set (incorrectly with regard to how we were told)
  • Barbara and I tried the mirrors out for the master and #3 baths
  • Atlantic glass came and measured for the downstairs bath #2 mirrors today
  • Mantle was built today











Monday, August 24, 2009

Monday 20090824

It's been a couple of days since we were able to get photos and post, but lots has been done.
  • all the tile work is finished, including the fireplace surround
  • the stair treads and risers are in
  • the hand rail along the stairwell upstairs is in
  • we might change the master bath paint color to a brown
  • the wainscoting is finished in bath #3
  • almost all the exterior trim is finished